01
ONGOING PROJECT
Our completed projects, together with the Founder’s previous professional experience during his tenure as Co-Founder of RD Construction.
Projects currently under execution by IRD Infratech.
The following five projects were completed under IRD Infratech.
The following 24 projects were successfully executed by our Founder during his tenure as Co-Founder of RD Construction and represent his prior professional experience.
| S. No. | Project Name | Location | Client | Cost (₹ Lacs) | Year |
|---|---|---|---|---|---|
| 01 | 4-Laning of Kodinar–Veraval Project, NH-8E – Supply, Design, Drawing & Crash Barrier | District Gir Somnath, Gujarat | Agroh Infrastructure Projects Pvt. Ltd. | ₹ 720.50 | 2022–23 |
| 02 | Construction & Upgradation of Bijnor–Kotawali Section, NH-709AD (Km 153.660 to Km 175.280) – Soil Works | Bijnor, Uttar Pradesh | Mathiyan Construction Pvt. Ltd. | ₹ 220.00 | 2022–23 |
| 03 | ROB 10A, Mirzapur – Drawing, Design & Material | Mirzapur | U.P. State Bridge Corporation Ltd. | ₹ 158.42 | 2021–22 |
| 04 | ROB 78A, Bakshi Bandh – Drawing, Design & Material | Allahabad | U.P. State Bridge Corporation Ltd. | ₹ 75.00 | 2021–22 |
| 05 | Saharanpur 2 & 3 – Drawing, Design & Material | Saharanpur | Saharanpur Smart Cities Ltd. | ₹ 248.87 | 2020–21 |
| 06 | Bridge Construction – Chhatrapul, Saharanpur | Saharanpur | Saharanpur Smart Cities Ltd. | ₹ 152.45 | 2020–21 |
| 07 | ROB 29B & 27C – Design, Drawings & Material | Allahabad | U.P. State Bridge Corporation Ltd. | ₹ 371.92 | 2020–21 |
| 08 | 6-Laning of Thaliparambha–Muzhappilangad Section of NH-66 (Project Length: 29.948 km) | Kerala | Vishwa Samudra Eng. Pvt. Ltd. | ₹ 359.10 | 2020–21 |
| 09 | Balance Works NH-72, Railway Underpass – Supply, Drilling & Installation of Anchor Bolts for Protection Works | Motichur, Haridwar | U.P. State Bridge Corporation Ltd. | ₹ 250.00 | 2020–21 |
| 10 | Balance Work NH-72 – RE Wall, Crash Barrier, Drawing, Design, Materials, Road Furnishing & Protection Work | Uttarakhand | U.P. State Bridge Corporation Ltd. | ₹ 793.68 | 2019–20 |
| 11 | ROB 543 – Design, Drawings & Material with Crash Barrier | Mathura | U.P. State Bridge Corporation Ltd. | ₹ 170.00 | 2019–20 |
| 12 | ROB 68B – Design, Drawings & Material with Crash Barrier | Agra | U.P. State Bridge Corporation Ltd. | ₹ 250.00 | 2019–20 |
| 13 | Alaknanda Gram Upalada, Srinagar – Supply, Drilling & Installation of Anchor Bolts for Protection Works | Uttarakhand | Mathiyan Construction Pvt. Ltd. | ₹ 950.00 | 2019–20 |
| 14 | NH-91 Aligarh–Kanpur – RS Wall Construction | Mainpuri, U.P. | APCO Infratech Pvt. Ltd. | ₹ 180.00 | 2019–20 |
| 15 | ROB 35B – Design, Drawings & Material with Crash Barrier | Allahabad | U.P. State Bridge Corporation Ltd. | ₹ 129.00 | 2018–19 |
| 16 | ROB 38D – Design, Drawings & Material with Crash Barrier | Allahabad | U.P. State Bridge Corporation Ltd. | ₹ 129.00 | 2018–19 |
| 17 | ROB 16B – Design, Drawings & Material with Crash Barrier | Bulandshahr | U.P. State Bridge Corporation Ltd. | ₹ 80.00 | 2018–19 |
| 18 | ROB Murga Phatak – Design, Drawings & Material with Crash Barrier | Allahabad | U.P. State Bridge Corporation Ltd. | ₹ 112.00 | 2017–18 |
| 19 | ROB Firozabad – Design, Drawings & Material | Firozabad | U.P. State Bridge Corporation Ltd. | ₹ 100.00 | 2016–17 |
| 20 | ROB Kuberpur – Design, Drawings & Material | Kuberpur | U.P. State Bridge Corporation Ltd. | ₹ 200.00 | 2016–17 |
| 21 | ROB Mathura – Design, Drawings & Material | Mathura | U.P. State Bridge Corporation Ltd. | ₹ 130.00 | 2016–17 |
| 22 | ROB 65, Firozabad – Design, Drawings & Material | Firozabad | U.P. State Bridge Corporation Ltd. | ₹ 80.00 | 2015–16 |
| 23 | ROB Dadri – Design, Drawings & Material | Dadri | U.P. State Bridge Corporation Ltd. | ₹ 75.00 | 2015–16 |
| 24 | Rohtak Road | Meerut | U.P. State Bridge Corporation Ltd. | ₹ 75.00 | 2013–14 |